Activity Report

Villagers are smiling with satisfaction now!

Dec 11, 2017

The road construction and/or rehabilitation works which is the one of support activities of Good Earth Japan (GEJ) extending to villages in Battambang Province northwest of the Kingdom of Cambodia where are the post mine field had been commenced in June this year. Those works are the part of GEJ’s action plan for 2017.
However, completion of those construction and/or rehabilitation works of roads have been delayed due to the short supply of the equipment for the works, and heavy and daily rain since then.
Now, just in early December, the rehabilitation work with Latelite coverage on the earth road at Boursankrea village has been completed finally.

Villagers were worried about when the road would be completed for long time. But thanks to the recovery of the weather and improvement on equipment supply, the works has been completed and happy smile appeared in their faces.

GEJ support farmers who live on the post minefield to become independent through agriculture training, improving living environment, and also improvement of infrastructure.

Before the work started. When rain, it become very muddy and difficult to pass around.

Culvert was installed by the end of June but …  Planned to complete by Aug. but not yet finished
                                 by the end of Oct.

As rain became calm around early Nov., Latelite laying and compaction works have been completed